From: route@monster.com
Sent: Friday, April 08, 2016 12:07 PM
To: hg@apeironinc.com
Subject: Please review this candidate for: p6 PMP
This resume has been forwarded to
you at the request of Monster User xapeix03
|
|||||||
|
|||||||
|
|
|
||||||
|
||||||
|
George W. Davis III 130 Marble Bluff Dr Kingston, TN. 37763 (208) 520-8799 L_gdavis@yahoo.com
To apply my nuclear
business management experience to a challenging nuclear work environment.
Diverse
project management and scheduling background. Propensity towards
leadership positions with a goal oriented mentality. I am performance
driven, and consistently exceed expectations. EXPERIENCE Advanced
Test Reactor Major Outage Planning & Integration Lead
March 2012 to January 2014
Battelle
Energy Alliance (BEA), Idaho National Laboratory (INL), Idaho – Managed the preparation for the
upcoming Core Internal Change out (CIC) outage at the Advanced Test Reactor
(ATR). Using Primavera P6, I developed the pre-CIC schedule to address
all major core component procurements, tooling fabrication, procedure
revisions, training activities, etc. Mentored a project coordinator to
learn the basics of P6 and take over the pre-CIC schedule and manage it going
forward. Also worked to assign the level of detail needed for the core
component replacement activities in the CIC execution schedule.
Mentored a Senior Reactor Operator to learn the basics of P6 and take over
the ongoing effort to define the execution schedule logic, activity duration and
resource loading. The CIC execution schedule is by far the most complex
schedule I have ever been associated with. There are space constraints
for staging of components; resource constraints, multiple shift calendars,
procedure prerequisites, and so on that have to be defined in P6 and logic
tied. This P6 schedule would need to be bullet proof to defend the cost
and timeline for this major outage. While personally using P6 to assess
schedule maturity, I also was responsible for the efforts of a team of engineers,
planners, operators, contract, procurement and maintenance personnel in the
preparation of this significant project. Preparations for this 6 month
outage includes the procurement of critical reactor components, review and
approval of 150+ procedures, the checkout and repair of special tools used to
disassemble the highly radioactive reactor core components, the development
of all work orders applicable to this outage, the coordination and scheduling
of all work, the training of all operators to qualify for this unique once
every 10 year event and the budget development and submittal to the
department of energy.
Work Execution
Manager
April 2010 to Feb. 2012
BEA,
INL, Idaho –Work execution manager at the Advanced Test Reactor
(ATR). Responsible for the implementation of the P6 T-week schedule
process which includes supervision of 4 work week managers, two production
coordinators, a project scheduler, an outage scheduler and a daily
scheduler. Personally used P6 to review the various project schedules
that would migrate onto the T-week schedule to assess their maturity and
validity. Used P6 to run resource reports to assess resource conflicts
on future work and prioritize which projects and plant work was mature enough
to be included in scope freeze for any given work week. Worked with
engineering, operations and maintenance to improve the T-week process and
apply principles of AP-928 to what will work at ATR based on staffing and
funding limitations. This effort culminated in a revision to the T-week
procedure and improvements to schedule performance and scope stability
percentages. Led outage preparations, critical path analysis, and
management presentations of outage progress for all the scheduled outages in
this time period. This included defining key objectives and deferring
work based on resource limitations. Work Week
Manager
January 2009 to March
2010 BEA,
INL, Idaho - Worked as a work week
manager at the Advanced Test Reactor (ATR). Responsible for
verifying all maintenance work was ready to be performed before assigning the
activity to the P6 plan of the week. Responsible for coordinating
maintenance, engineering, planning and project work such that the work can be
executed as scheduled. Led the plan of the day meetings and worked to
maintain schedule compliance throughout the assigned work week.
Developed codes and filters in P6 to aid each work week manager in
communicating status on a given task. Also created standard P6 reports
for engineering and planning to prepare work on a coordinated basis.
Transitioned the production control department from using Excel spreadsheets
to working live in P6 during outage scope freeze meetings. This
eliminated the use of multiple data bases and the constant need to reconcile
data between P6 and Excel. Project
Manager
April 2006 to December 2008 BEA,
INL, Idaho – Worked as the project
manager on both the new 130,000 square foot Research and Education Laboratory
under a design/build/lease arrangement and on the Materials and Fuels Complex
Zero Power Physics Reactor (ZPPR) deactivation project. Developed the
project execution plan for ZPPR as defined by the funding source.
Determined the waste disposition path, acquisition strategy, characterization
of the reactor components, and the engineering plan for deactivating the
ZPPR. Programmed all the lab spaces in the new research laboratory by
working with the stakeholders and department managers. Also worked with
the stakeholders to determine the location for this new laboratory. Project Manager
May 2005 to March 2006
CH2M-WG,
INL, Idaho – Defined the $25 million life cycle
baseline scope to complete the decommissioning of the high risk Loss of Fluid
Test (LOFT) complex. Personally developed the LOFT D&D schedule
using P3. Established the sub-contract strategy for completing
demolition of the LOFT complex in less than two years. Started negotiations
with the customer and BEA to establish the demolition boundaries and end
state of LOFT and the BEA attached building for specific manufacturing
capability (SMC). Also worked as control account manager for the
decommissioning of the LOFT high level waste underground storage tanks.
Conceived the strategy for managing the underground tanks and ultimately was
able to lead a team to achieve a clean demolition. Managed $8 million
of FY06 scope associated with eleven decommissioning work packages at
TAN. Led functional teams across technical disciplines to
translate decommissioning strategy into implementation.
Project
Manager
April 2004 to April 2005 Bechtel
(BBWI), INL, Idaho – Managed three
control account managers and a diversified functional team of 50+ personnel
on the successful completion of a $10 million deactivation campaign at the
LOFT complex in an eleven month time frame. Earned $2.1 of a
possible $2.2 million in fee for the deactivation scope, which included the
removal of over 17K linear feet of contaminated piping systems and the
demolition of 15 buildings. Managed the project scope from the planning
stages through project delivery and closeout. Coordinated the efforts
of sub-contractors, crafts, operators, radcon, scheduling, planners,
production coordinators, construction and engineering to aggressively address
the deactivation of LOFT facilities. Led a team through the development
of the LOFT end state document and negotiated with the customer on the decommissioning
scope to make the document binding. Led a project team to successfully
complete the voluntary consent order closure plan at LOFT, 9 months ahead of
schedule. Planning and
controls
July 1999 to April 2004
Bechtel
(BBWI), INL, Idaho – Increased
level of responsibility applied to scheduling work at the INEL. Most
recently worked as the P3 scheduling lead at the Test Area North (TAN) clean
and close project. Responsibilities included over seeing the work of up
to four project schedulers responsible for over $50 million in scope. Performed
critical path analysis and developed resource profiles to help management
manage scope and schedule. Led the P3 project scheduling efforts on the
Glove box Excavation Method (GEM) project at the Radiological Waste
Management Complex (RWMC), prior to the lead role at TAN. Responsible
for insuring all procedural and regulatory requirements were assigned,
scoped, and logic tied to their respective driving activities.
Performed critical path analysis and worked with management to insure the 5
million in fee would be achieved. Chaired daily meetings with
operations to insure the P3 schedule was understood and the priority work
accomplished. Prior to the GEM project, directed the efforts of four P3
schedulers working the 3100 CM project at RWMC. Prior to RWMC, worked
as a work window specialist at Idaho Nuclear Technology and Engineering
Center (INTEC scheduler), which entailed creating the plan of the week,
determining maintenance and operations priorities, over seeing a scheduler
and assisting the planning department with work order priorities for the High
Level Waste facility. As a scheduler, I developed the turnaround
schedule used to coordinate work activities associated with the start up of
the calciner for its final campaign. Operations
Supervisor
November 1994 to
June 1999 Newport
News Reactor Services, INL Navel Reactor Facility (NRF), Idaho – Managed the development of functional teams
across technical disciplines to perform the $74 million A1W-3A and S5G
reactor defueling & decommissioning project. Directed the
functional teams through all aspects of defueling operations; from equipment
checkout, quality control, procedure development, defueling team
qualifications to the actual defueling operations. Led the
implementation of DOD’s request to deviate from past practices of performing
defueling operations in full anti-contamination clothing, to the more technically
challenging engineered drape approach. Guided the efforts of
multi-technical disciplines to design, test and qualify engineered drapes for
all aspects of defueling operations on the S5G reactor. Designed an
inner tube containment system to be used in the tight quarters surrounding
the standpipes and oversaw the design from conception to
implementation. The new engineered drape approach was so successful
that it was implemented on the defueling of the naval submarine Narwhal
several years later. Successfully led an organization through the
defueling of the S5G reactor ahead of schedule and with no spread of
contamination outside the designed engineered drapes. Developed and
implemented the training program to train all newly hired crafts and management
to the safety standards applicable to this facility. Also, developed
the lesson plans for training the electricians on the maintenance of the A1W
gantry crane. EDUCATION Bachelor of Science, Business
Management
Christopher
Newport College, Newport News, VA,
GPA: 3.5, Major GPA: 3.5 Professional
Certifications Project
Manager Professional (PMP)
|
|
|
||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Languages: |
Languages |
Proficiency Level |
|
English |
Fluent |
|
|
|